Contract Agreement Amount

Rs. 8,07,01,667

Physical Progress

0.00%

Financial Progress

98.53%

Remaining Payment

Rs. 1

Maintenance of Araniko Highway 80+000 to 86+000

Office: डिभिजन सडक कार्यालय, दोलखा (18)

Fiscal Year: 075-76

0.00%

Contract Date: 18-Mar-19

Start Date: 18-Mar-19

Completion Date: 19-Jun-2019 (EOT Not Done)

Project Description

No description available.