Contract Agreement Amount
Rs. 9,93,13,783
Physical Progress
0.00%
Financial Progress
98.53%
Remaining Payment
Rs. 1
Bridge Construction works over Babai Khola along Lamahi - Tulsipur Road in Dang District.
Office: सडक डिभिजन, दाङ्ग (31)
Fiscal Year: 072-73
Contract Date: 31-Jan-16
Start Date: 31-Jan-16
Completion Date: 27-Feb-2020 (EOT Done)
Project Description
No description available.