Contract Agreement Amount
Rs. 99,57,338
Physical Progress
0.00%
Financial Progress
98.50%
Remaining Payment
Rs. 1
Roadway Excavation , Structural and Cross drainage works on Beldada-Dhunganabesi Section of Rampur Arunkhola Road Palpa
Office: सडक डिभिजन, पाल्पा (27)
Fiscal Year: 076-77
Contract Date: 3-Jan-20
Start Date: 17-Jan-20
Completion Date: 11-Dec-2020 (EOT Done)
Project Description
No description available.