Contract Agreement Amount

Rs. 2,92,72,976

Physical Progress

0.00%

Financial Progress

98.48%

Remaining Payment

Rs. 1

Construction of RCC bridge over Kanari Khola

Office: हुलाकी राजमार्ग आयोजना, योजना कार्यालय, धनगढी, कैलाली (169)

Fiscal Year: 072-73

0.00%

Contract Date: 14-Jul-16

Start Date: 30-Jul-16

Completion Date: 05-Jul-2019 (EOT Done)

Project Description

No description available.