Contract Agreement Amount

Rs. 88,64,936

Physical Progress

97.20%

Financial Progress

98.47%

Remaining Payment

Rs. 1

Pavement Works Including Retaining Structure along Gramthan-7 Bajrangbali-Nahar Sadak, Morang

Office: यान्त्रिक कार्यालय, चितवन (46)

Fiscal Year: 079-80

97.20%

Contract Date: 26-May-23

Start Date: 26-May-23

Completion Date: 26-May-2023 (EOT Not Done)

Project Description

No description available.