Contract Agreement Amount

Rs. 2,17,70,098

Physical Progress

0.00%

Financial Progress

98.47%

Remaining Payment

Rs. 1

Shribagar Nijayang Bridge

Office: दार्चुला टिङकर सडक योजना, दार्चुला (106)

Fiscal Year: 072-73

0.00%

Contract Date: 17-Feb-16

Start Date: 24-Feb-16

Completion Date: 05-Dec-2020 (EOT Done)

Project Description

No description available.