Contract Agreement Amount
Rs. 6,58,89,151
Physical Progress
100.00%
Financial Progress
98.45%
Remaining Payment
Rs. 1
Road Upgrading works along Bhumahi-Parasi-Bhairahawa
Office: केन्द्रिय सडक प्रयोगशाला, ललितपुर (52)
Fiscal Year: 078-79
Contract Date: 18-Aug-22
Start Date: 18-Aug-22
Completion Date: 19-Aug-2023 (EOT Not Done)
Project Description
No description available.