Contract Agreement Amount

Rs. 5,79,01,279

Physical Progress

100.00%

Financial Progress

98.44%

Remaining Payment

Rs. 1

Construction of Prestressed RCC Bridge over Banke River (1 no *40m span, total length 41.2 m) along Hardi Malangwa Road, Sarlahi

Office: हुलाकी राजमार्ग आयोजना, योजना कार्यालय, जनकपुर​, धनुषा (213)

Fiscal Year: 072-73

100.00%

Contract Date: 8-Jul-16

Start Date: 8-Jul-16

Completion Date: 13-Jan-2021 (EOT Done)

Project Description

No description available.