Contract Agreement Amount

Rs. 2,28,50,015

Physical Progress

98.41%

Financial Progress

98.41%

Remaining Payment

Rs. 1

Bridge over Kumale Khola along Surkhet-Kalikot-Jumla Road in Sattale VDC-1, Dailekh

Office: सडक डिभिजन, सुर्खेत (33)

Fiscal Year: 073-74

98.41%

Contract Date: 30-May-17

Start Date: 30-May-17

Completion Date: 01-Sep-2018 (EOT Not Done)

Project Description

No description available.