Contract Agreement Amount
Rs. 3,18,10,056
Physical Progress
98.41%
Financial Progress
98.41%
Remaining Payment
Rs. 1
Construction of Shiwalaya Khola Bridge along Patibhanjyang- Chahare Road Section of Midhill Highway,Nuwakot (RCC 1*25)
Office: Puspalal (Midhill) Road Project, Gorkha (275)
Fiscal Year: 077-78
Contract Date: 11-Feb-21
Start Date: 11-Feb-21
Completion Date: 09-Jan-2023 (EOT Done)
Project Description
No description available.