Contract Agreement Amount
Rs. 3,16,18,742
Physical Progress
100.00%
Financial Progress
98.38%
Remaining Payment
Rs. 1
TilotammaChakrapath (Jogikuti-TilottamaGaushala-ShivapurChowk-Sishaughari-Kanchibazar-LakhanThapaChowk-Tikuligadhi-Anandaban-Shankarnagar-Jogikuti Road)
Office: सडक डिभिजन, वुटवल (28)
Fiscal Year: 078-79
Contract Date: 10-Feb-22
Start Date: 11-Feb-22
Completion Date: 11-Feb-2022 (EOT Not Done)