Contract Agreement Amount

Rs. 53,39,561

Physical Progress

100.00%

Financial Progress

98.34%

Remaining Payment

Rs. 1

Road Upgrading Works on Suryabinayak (Purano buspark) Trolly buspark Sundarbasti Paandubazar sadak, Bhaktapur

Office: सडक डिभिजन, भक्तपुर (24)

Fiscal Year: 076-77

100.00%

Contract Date: 22-Dec-19

Start Date: 22-Dec-19

Completion Date: 08-Mar-2020 (EOT Not Done)

Project Description

No description available.