Contract Agreement Amount
Rs. 19,96,650
Physical Progress
0.00%
Financial Progress
98.34%
Remaining Payment
Rs. 1
Road Upgrading works along Bhalukhop-Khudnabari Road, Ilam
Office: डिभिजन सडक कार्यालय, ईलाम (12)
Fiscal Year: 076-77
Contract Date: 1-Mar-20
Start Date: 1-Mar-20
Completion Date: 09-Jul-2020 (EOT Not Done)
Project Description
No description available.