Contract Agreement Amount

Rs. 23,15,30,508

Physical Progress

100.00%

Financial Progress

98.31%

Remaining Payment

Rs. 1

upgrading of manmat kalaiya matiyarwa road UR015

Office: हुलाकी राजमार्ग निर्देशनालय​, काठमाण्डौ (230)

Fiscal Year: 072-73

100.00%

Contract Date: 19-Oct-16

Start Date: 2-Nov-16

Completion Date: 31-Dec-2020 (EOT Done)

Project Description

No description available.