Contract Agreement Amount
Rs. 53,08,662
Physical Progress
0.00%
Financial Progress
0.00%
Remaining Payment
Rs. 100
Rective Maintenance Works on Sanfe-Barjugaad(CH-0+000 to CH 27+000) Road Section
Office: सडक विभाग, काठमाण्डौ (2)
Fiscal Year: 081-82
Contract Date: 25-Aug-24
Start Date: 25-Aug-24
Completion Date: 24-Dec-2024 (EOT Not Done)
Project Description
No description available.