Contract Agreement Amount
Rs. 3,44,60,794
Physical Progress
100.00%
Financial Progress
98.27%
Remaining Payment
Rs. 1
Construction of RCC 2-web slab deck Phagam khola bridge along Sulichaur Phagam Road
Office: Road Division, Pyuthaan (258)
Fiscal Year: 073-74
Contract Date: 24-Apr-17
Start Date: 24-Apr-17
Completion Date: 27-Aug-2018 (EOT Not Done)
Project Description
No description available.