Contract Agreement Amount

Rs. 64,06,50,885

Physical Progress

100.00%

Financial Progress

98.26%

Remaining Payment

Rs. 1

घाटगाउँ कर्णाली मोटरेवल पुल (कैलाली चिप्लेघाट बडीगाउँ जोड्ने पुल)

Office: पुल योजना, पश्चिम क्षेत्र सेक्टर नं. ३, वांके (190)

Fiscal Year: 073-74

100.00%

Contract Date: 13-Dec-17

Start Date: 13-Dec-17

Completion Date: 08-Jun-2022 (EOT Done)

Project Description

No description available.