Contract Agreement Amount

Rs. 50,89,750

Physical Progress

98.24%

Financial Progress

98.24%

Remaining Payment

Rs. 1

Road Upgrading works along Sulichaur-Kavara-Mangha-Kwaligau Sadak in Rolpa

Office: Road Division, Pyuthaan (258)

Fiscal Year: 078-79

98.24%

Contract Date: 8-Jun-22

Start Date: 8-Jun-22

Completion Date: 08-Jun-2022 (EOT Not Done)

Project Description

No description available.