Contract Agreement Amount

Rs. 46,13,34,266

Physical Progress

98.50%

Financial Progress

98.24%

Remaining Payment

Rs. 1

Upgrading with widening of Shahidmarga, Ghartigaon - Thawang Road Section (chainage 95+000 to 104+500,117+000 to 140+000)

Office: शहीद मार्ग सडक योजना, रोल्पा (93)

Fiscal Year: 073-74

98.50%

Contract Date: 7-Jun-17

Start Date: 8-Jun-17

Completion Date: 20-Nov-2022 (EOT Done)