Contract Agreement Amount
Rs. 22,59,907
Physical Progress
0.00%
Financial Progress
98.23%
Remaining Payment
Rs. 1
Maryadpur Sitalpur Mewa Sadak, Rautahat
Office: डिभिजन सडक कार्यालय, चन्द्रनिगाहापुर, गौर (176)
Fiscal Year: 076-77
Contract Date: 24-Feb-20
Start Date: 24-Feb-20
Completion Date: 23-Jun-2020 (EOT Not Done)
Project Description
No description available.