Contract Agreement Amount
Rs. 38,38,554
Physical Progress
98.23%
Financial Progress
98.23%
Remaining Payment
Rs. 1
Pavement Works along Baklauri Panchayat bata Dharan 8 ko Hariyali jodne sadak dharan, Sunsari
Office: सडक डिभिजन, पाल्पा (27)
Fiscal Year: 080-81
Contract Date: 29-Jan-24
Start Date: 29-Jan-24
Completion Date: 08-Jul-2024 (EOT Not Done)
Project Description
No description available.