Contract Agreement Amount

Rs. 11,17,700

Physical Progress

100.00%

Financial Progress

98.22%

Remaining Payment

Rs. 1

Road upgrading works at Gadgade lamidada Bakrigaun road nagarkot

Office: सडक डिभिजन, भक्तपुर (24)

Fiscal Year: 077-78

100.00%

Contract Date: 18-Feb-21

Start Date: 18-Feb-21

Completion Date: 04-Jun-2021 (EOT Not Done)

Project Description

No description available.