Contract Agreement Amount
Rs. 11,17,700
Physical Progress
100.00%
Financial Progress
98.22%
Remaining Payment
Rs. 1
Road upgrading works at Gadgade lamidada Bakrigaun road nagarkot
Office: सडक डिभिजन, भक्तपुर (24)
Fiscal Year: 077-78
Contract Date: 18-Feb-21
Start Date: 18-Feb-21
Completion Date: 04-Jun-2021 (EOT Not Done)
Project Description
No description available.