Contract Agreement Amount
Rs. 5,04,74,344
Physical Progress
96.29%
Financial Progress
98.20%
Remaining Payment
Rs. 1
Shanidev Nirman Sewa Pvt.ltd, Kanchanpur
Office: दार्चुला टिङकर सडक योजना, दार्चुला (106)
Fiscal Year: 078-79
Contract Date: 19-Oct-21
Start Date: 19-Oct-21
Completion Date: 18-Mar-2024 (EOT Done)
Project Description
No description available.