Contract Agreement Amount

Rs. 21,45,641

Physical Progress

98.19%

Financial Progress

98.19%

Remaining Payment

Rs. 1

Specific Maintenance work along Mawa-Harainchamod section (MRM)

Office: डिभिजन सडक कार्यालय, मोरङ (14)

Fiscal Year: 079-80

98.19%

Contract Date: 16-Oct-22

Start Date: 17-Oct-22

Completion Date: 13-Apr-2023 (EOT Done)

Project Description

No description available.