Contract Agreement Amount
Rs. 5,85,800
Physical Progress
0.00%
Financial Progress
98.00%
Remaining Payment
Rs. 2
Construction of Plum Concrete & Gabion works in Khahare Bridge Protection works
Office: डिभिजन सडक कार्यालय, खुर्कोट (185)
Fiscal Year: 077-78
Contract Date: 7-Mar-21
Start Date: 14-Mar-21
Completion Date: 14-Jun-2021 (EOT Not Done)
Project Description
No description available.