Contract Agreement Amount
Rs. 6,14,33,383
Physical Progress
80.00%
Financial Progress
98.00%
Remaining Payment
Rs. 2
Bridge Construction Work (Psc Girder ) over karra River along Chuche Khola bazzar-Baraute, Road Hetauda Makwanpur
Office: डिभिजन सडक कार्यालय, मकवानपुर (19)
Fiscal Year: 074-75
Contract Date: 5-Jun-18
Start Date: 5-Jun-18
Completion Date: 05-Jun-2018 (EOT Not Done)
Project Description
No description available.