Contract Agreement Amount

Rs. 1,30,41,365

Physical Progress

100.00%

Financial Progress

97.95%

Remaining Payment

Rs. 2

Periodic Maintenance Works in Mahakali Highway(Faltude-Gaira Section)

Office: सडक डिभिजन, डोटी (35)

Fiscal Year: 074-75

100.00%

Contract Date: 5-Mar-18

Start Date: 19-Mar-18

Completion Date: 12-Jun-2020 (EOT Done)

Project Description

No description available.