Contract Agreement Amount

Rs. 94,60,786

Physical Progress

97.83%

Financial Progress

97.93%

Remaining Payment

Rs. 2

Reactive Maintenance Works on Dumre Besisahar Road [ Ch 12+000 - 15+000] Tanahun

Office: डुम्रे बेसीशहर चामे सडक योजना, बेसीशहर लमजुङ (299)

Fiscal Year: 078-79

97.83%

Contract Date: 4-Feb-22

Start Date: 4-Feb-22

Completion Date: 08-Oct-2022 (EOT Done)

Project Description

No description available.