Contract Agreement Amount
Rs. 17,42,49,911
Physical Progress
41.00%
Financial Progress
97.92%
Remaining Payment
Rs. 2
Design & Build of Trishuli River Bridge at Baireni, Kalleri, Syaltar, Dhading
Office: पुल योजना, मध्य क्षेत्र सेक्टर नं. २, काठमाण्डौ (189)
Fiscal Year: 072-73
Contract Date: 15-Jul-16
Start Date: 15-Jul-16
Completion Date: 12-Jul-2021 (EOT Done)