Contract Agreement Amount
Rs. 70,05,086
Physical Progress
0.00%
Financial Progress
97.91%
Remaining Payment
Rs. 2
Roadway Excavation, Structural and Cross Drainage Works on Syaulibazar - Bardakot - Mityal Road [Bardakot - Mityal Section], Palpa
Office: सडक डिभिजन, पाल्पा (27)
Fiscal Year: 076-77
Contract Date: 4-Jun-20
Start Date: 18-Jun-20
Completion Date: 14-Dec-2020 (EOT Done)
Project Description
No description available.