Contract Agreement Amount

Rs. 19,61,595

Physical Progress

97.91%

Financial Progress

97.91%

Remaining Payment

Rs. 2

Specific Maintenance and Road Saftey along MRM (Sunsari Bridge (110+000-Koshi Barrage Section(135+000))

Office: सडक डिभिजन, सुर्खेत (33)

Fiscal Year: 080-81

97.91%

Contract Date: 29-Feb-24

Start Date: 29-Feb-24

Completion Date: 08-Jul-2024 (EOT Not Done)