Contract Agreement Amount

Rs. 62,53,400

Physical Progress

0.00%

Financial Progress

0.00%

Remaining Payment

Rs. 100

Reactive Maintenance Works along Rapti Highway (Shitalpur-Tulsipur-Gotikhola Section ) Road in Dang District.

Office: योजना तथा अनुगमन महाशाखा (भूवातावरण तथा सामाजिक शाखा) (4)

Fiscal Year: 079-80

0.00%

Contract Date: 6-Dec-22

Start Date: 6-Dec-22

Completion Date: 13-Apr-2023 (EOT Not Done)

Project Description

No description available.