Contract Agreement Amount
Rs. 1,15,23,498
Physical Progress
97.80%
Financial Progress
97.83%
Remaining Payment
Rs. 2
Upgrading/Improvement of Ratanmare Sautamare Road Section (Ch: 90+300 to 96+900) along Saljhandhi Sandhikharka Dhorpatan Road NH-52
Office: योजना तथा अनुगमन महाशाखा (भूवातावरण तथा सामाजिक शाखा) (4)
Fiscal Year: 079-80
Contract Date: 7-Dec-22
Start Date: 7-Dec-22
Completion Date: 03-Jun-2023 (EOT Not Done)
Project Description
No description available.