Contract Agreement Amount

Rs. 13,96,900

Physical Progress

95.00%

Financial Progress

97.79%

Remaining Payment

Rs. 2

Supply work of Construction materials at DRO Lalitpur

Office: डिभिजन सडक कार्यालय, ललितपुर (23)

Fiscal Year: 079-80

95.00%

Contract Date: 29-Aug-22

Start Date: 29-Aug-22

Completion Date: 27-Oct-2022 (EOT Not Done)

Project Description

No description available.