Contract Agreement Amount

Rs. 28,08,924

Physical Progress

100.00%

Financial Progress

97.75%

Remaining Payment

Rs. 2

Road improvement works of dandagaun-bancharedanda-katunje-jyamire-jibanpur Road, Nuwakot

Office: सडक डिभिजन, सुर्खेत (33)

Fiscal Year: 079-80

100.00%

Contract Date: 29-Jan-23

Start Date: 29-Jan-23

Completion Date: 30-Jun-2023 (EOT Not Done)

Project Description

No description available.