Contract Agreement Amount
Rs. 34,49,790
Physical Progress
0.00%
Financial Progress
97.70%
Remaining Payment
Rs. 2
Roadway Upgrading Works on Tarkughat Moriya Pyarjung Bichaur Road , Lamjung.(ch:7+140-7+510).
Office: सडक डिभिजन, तनहुं (25)
Fiscal Year: 076-77
Contract Date: 23-Jan-20
Start Date: 23-Jan-20
Completion Date: 13-Apr-2022 (EOT Done)
Project Description
No description available.