Contract Agreement Amount
Rs. 61,91,574
Physical Progress
0.00%
Financial Progress
0.00%
Remaining Payment
Rs. 100
Reactive Maintenance Of Road Surface in Khodpe-Chainpur Section of Khodpe-Chainpur Highway NH64 ch 0+000-108+000
Office: डिभिजन सडक कार्यालय, झापा (13)
Fiscal Year: 080-81
Contract Date: 21-Dec-23
Start Date: 21-Dec-23
Completion Date: 12-May-2024 (EOT Not Done)
Project Description
No description available.