Contract Agreement Amount
Rs. 13,49,892
Physical Progress
0.00%
Financial Progress
97.68%
Remaining Payment
Rs. 2
Road Upgrading Works along Sallaghari Khiu Tol Banachaur Raut Gaun Hattigauda Sadak
Office: सडक डिभिजन, भक्तपुर (24)
Fiscal Year: 077-78
Contract Date: 15-Feb-21
Start Date: 15-Feb-21
Completion Date: 01-Jun-2021 (EOT Not Done)
Project Description
No description available.