Contract Agreement Amount
Rs. 44,11,21,733
Physical Progress
100.00%
Financial Progress
97.68%
Remaining Payment
Rs. 2
upgrading of tamagadhi simraungadh road bara 073.74.UR020 ch 20+000-39+745
Office: हुलाकी राजमार्ग निर्देशनालय, काठमाण्डौ (230)
Fiscal Year: 073-74
Contract Date: 1-Jun-17
Start Date: 1-Jun-17
Completion Date: 08-Dec-2019 (EOT Done)
Project Description
No description available.