Contract Agreement Amount

Rs. 84,90,405

Physical Progress

100.00%

Financial Progress

97.62%

Remaining Payment

Rs. 2

Upgrading/Improvement of Road by Construction of Drain, Road Structure and Rigid Pavement Works at Ch: 147+700 to Ch: 149+600, DeuraliDadakateri Section along PyuthanSurkhet Road NH-19 Arghakhanchi

Office: योजना तथा अनुगमन महाशाखा (योजना अनुगमन तथा मुल्यांकन शाखा) (3)

Fiscal Year: 079-80

100.00%

Contract Date: 30-Nov-22

Start Date: 30-Nov-22

Completion Date: 30-Nov-2022 (EOT Not Done)

Project Description

No description available.