Contract Agreement Amount
Rs. 12,68,608
Physical Progress
100.00%
Financial Progress
97.56%
Remaining Payment
Rs. 2
Road Upgrading Works on Piplabot Tajmot jane Bato ma Culvert Retaining Wall, Changunaryan-4, Bhaktapur
Office: सडक डिभिजन, भक्तपुर (24)
Fiscal Year: 076-77
Contract Date: 24-Nov-19
Start Date: 24-Nov-19
Completion Date: 12-Feb-2020 (EOT Not Done)
Project Description