Contract Agreement Amount
Rs. 34,35,099
Physical Progress
62.00%
Financial Progress
97.54%
Remaining Payment
Rs. 2
Construction work at Xhakrapath- Dholahiti (Chapagaun)Sadak
Office: डिभिजन सडक कार्यालय, धनुषा (17)
Fiscal Year: 079-80
Contract Date: 9-Dec-22
Start Date: 9-Dec-22
Completion Date: 07-Mar-2023 (EOT Not Done)
Project Description
No description available.