Contract Agreement Amount

Rs. 43,34,671

Physical Progress

100.00%

Financial Progress

97.47%

Remaining Payment

Rs. 2

Rigid Pavement Works at Dhulikhel-Sindhuli-Bardibas Road

Office: सूर्यविनायक-धुलिखेल​, धुलिखेल-सिन्धुली-बर्दिवास सडक आयोजना, काठमाण्डौ (225)

Fiscal Year: 078-79

100.00%

Contract Date: 3-Apr-22

Start Date: 3-Apr-22

Completion Date: 01-Aug-2022 (EOT Not Done)

Project Description

No description available.