Contract Agreement Amount

Rs. 5,11,91,554

Physical Progress

0.00%

Financial Progress

97.46%

Remaining Payment

Rs. 2

Construction of Pre-stressed Concrete Bridge (1X40 m) with open foundation over Durga Khola, Khidim, Arghakhanchi

Office: सालझण्डी सन्धिखर्क ढोरपाटन सडक योजना, अर्घाखांची (92)

Fiscal Year: 074-75

0.00%

Contract Date: 3-Apr-18

Start Date: 3-Apr-18

Completion Date: 24-Dec-2019 (EOT Not Done)

Project Description

No description available.