Contract Agreement Amount
Rs. 5,11,91,554
Physical Progress
0.00%
Financial Progress
97.46%
Remaining Payment
Rs. 2
Construction of Pre-stressed Concrete Bridge (1X40 m) with open foundation over Durga Khola, Khidim, Arghakhanchi
Office: सालझण्डी सन्धिखर्क ढोरपाटन सडक योजना, अर्घाखांची (92)
Fiscal Year: 074-75
Contract Date: 3-Apr-18
Start Date: 3-Apr-18
Completion Date: 24-Dec-2019 (EOT Not Done)
Project Description
No description available.