Contract Agreement Amount
Rs. 1,14,22,404
Physical Progress
96.00%
Financial Progress
97.37%
Remaining Payment
Rs. 2
Maintenance of Road by Construction of Roadway Structures, Humepipe Culverts, Slab Culverts and Earthworks in Bhuithan Danda-Harpe, Baglung (CH 158+500) to Devisthan, Baglung (Ch 164+000) section along Saljhandi-Sandikharka-Dhorpatan Road
Office: सालझण्डी सन्धिखर्क ढोरपाटन सडक योजना, अर्घाखांची (92)
Fiscal Year: 077-78
Contract Date: 3-May-21
Start Date: 3-May-21
Completion Date: 09-Apr-2022 (EOT Done)
Project Description
No description available.