Contract Agreement Amount

Rs. 30,68,08,021

Physical Progress

0.00%

Financial Progress

97.32%

Remaining Payment

Rs. 2

Upgrading of Nepalgunj Baghauda Road,Banke(CH 0+000-22+000)

Office: हुलाकी राजमार्ग आयोजना, योजना कार्यालय, वाके (98)

Fiscal Year: 073-74

0.00%

Contract Date: 2-Feb-17

Start Date: 16-Feb-17

Completion Date: 31-Jul-2020 (EOT Done)