Contract Agreement Amount
Rs. 54,24,259
Physical Progress
0.00%
Financial Progress
97.31%
Remaining Payment
Rs. 2
Roadway Excavation, Structural,Cross Drainage Works and Pavement works on Belbas-Nuwakot-Dovan Road , Palpa
Office: सडक डिभिजन, पाल्पा (27)
Fiscal Year: 076-77
Contract Date: 31-May-20
Start Date: 14-Jun-20
Completion Date: 11-Jan-2021 (EOT Done)
Project Description
No description available.