Contract Agreement Amount

Rs. 99,91,518

Physical Progress

97.00%

Financial Progress

97.27%

Remaining Payment

Rs. 2

Gabion and Plum works along alternative route, Balde (Emergency works)

Office: हेभिईक्युपमेन्ट डिभिजन, काठमाण्डौ (39)

Fiscal Year: 079-80

97.00%

Contract Date: 19-Jun-23

Start Date: 19-Jun-23

Completion Date: 16-Sep-2023 (EOT Not Done)

Project Description

No description available.