Contract Agreement Amount

Rs. 35,75,685

Physical Progress

0.00%

Financial Progress

97.22%

Remaining Payment

Rs. 2

M.R.M. Banke Dhansar Sada, Sarlahi, Rautahat

Office: डिभिजन सडक कार्यालय, चन्द्रनिगाहापुर, गौर (176)

Fiscal Year: 076-77

0.00%

Contract Date: 20-Nov-19

Start Date: 20-Nov-19

Completion Date: 16-Oct-2020 (EOT Done)

Project Description

No description available.