Contract Agreement Amount
Rs. 3,08,74,990
Physical Progress
0.00%
Financial Progress
0.00%
Remaining Payment
Rs. 100
Rapti Highway Shitalpati-Khaula Section (Ch 83+000 to 88+000)
Office: सडक डिभिजन, दाङ्ग (31)
Fiscal Year: 078-79
Contract Date: 28-Feb-22
Start Date: 28-Feb-22
Completion Date: 29-Dec-2022 (EOT Done)
Project Description
No description available.